Equinor Blames US Shipbuilding Delays for Late Offshore Wind Installation

The Norwegian energy company Equinor told investors and the media on Wednesday that its offshore wind project, Empire Wind, is approximately 80 percen...

2 min read
Equinor Blames US Shipbuilding Delays for Late Offshore Wind Installation
Photo: The Maritime Executive

The Norwegian energy company Equinor told investors and the media on Wednesday that its offshore wind project, Empire Wind, is approximately 80 percent complete but running behind schedule due to delays in U.S. shipbuilding. It said the delays were outside its control and that it now expects the wind farm off the coast of New York to deliver first power by mid-2027.

“On Empire Wind, despite the stop work orders, and all of that, we have been able to progress this and develop this, and it hasn’t really slowed us down much,” said CFO Torgrim Reitan during the investor conference call on October 28. He reported that top side construction is now expected to begin in late December, and the company expects first power during the first half of next year.

Equinor selected an installation system working with Maersk Wind, which built its installation vessel, Maersk Viridis, at Seatrium in Singapore. The massive 40,000 gross ton vessel had its own challenges in construction, with disputes with the shipyard. Those issues were resolved, and the vessel arrived off Pascagoula, Mississippi, in August. It is undergoing training and testing for its unique barge system.

The company told investors that it is waiting for the tugs and barges, which are being built in the United States. They blamed this for creating “a few months' delay” for the project.

This story was originally published by The Maritime Executive. Read the full story at The Maritime Executive →