First Nordseecluster B Monopiles Arrive at Dutch Port

RWE has received the first 10 monopile foundations for the 900 MW Nordseecluster B offshore wind project at the port of Eemshaven in the Netherlands.The foundations…

1 min read
First Nordseecluster B Monopiles Arrive at Dutch Port
Photo: Offshore Engineer

RWE has received the first 10 monopile foundations for the 900 MW Nordseecluster B offshore wind project at the port of Eemshaven in the Netherlands.

The foundations, manufactured and supplied by Dajin Heavy Industry, measure approximately 81 meters in length on average and weigh around 1,350 tonnes each.

A total of 60 monopiles for Nordseecluster B will be handled at Buss Ports' heavy-lift terminal in Eemshaven during 2026 and 2027, ahead of offshore installation.

Installation of the foundations is scheduled to begin in 2027, followed by the installation of 60 wind turbines in 2028. The project is expected to enter commercial operation in early 2029.

This story was originally published by Offshore Engineer. Read the full story at Offshore Engineer →