KTZ completes 93% of earthworks on the 303 km Bakhty–Ayagoz railway line.
Kazakhstan’s national railway company Kazakhstan Temir Zholy (KTZ) has reported that 93% of earthworks have been completed on the 303 km Bakhty–Ayagoz railway line currently under construction. Of the planned…
Kazakhstan’s national railway company Kazakhstan Temir Zholy (KTZ) has reported that 93% of earthworks have been completed on the 303 km Bakhty–Ayagoz railway line currently under construction. Of the planned 39.5 million cubic metres of earthworks, 36.8 million cubic metres have already been completed, with most of the remaining work concentrated in the border area and around Bakhty station. Construction is progressing according to schedule. Contractors are currently levelling the upper layer of the railway embankment and conducting soil compaction quality checks to prepare the sections for track installation.
Construction of engineering structures is also progressing. Of the 267 planned drainage culverts, 245 have been completed and another 15 are under construction. In addition, 12 of the 19 livestock crossings have been finished, while work is underway on 43 of the 47 railway bridges. To accelerate the project, bridge beams are being manufactured directly at the construction site in compliance with certification requirements and construction standards. Track materials are supplied by Kazakh manufacturers: rails are produced by the Aktobe Rail and Section Works, sleepers and fastening systems are provided by RWS Binding, Innotrack, Fasteners 2metall (BENT) and Magnetik, while railway switches are supplied by Prommashkomplekt. A materials reception and distribution facility has been established near Ayagoz station.
The new railway will establish a third rail border crossing between Kazakhstan and China – Bakhty–Pokitu – helping redistribute freight flows and reduce pressure on the existing Dostyk and Altynkol crossings, which are operating close to their capacity limits. The project is also expected to support transport infrastructure development and economic growth in Kazakhstan’s Abai Region. KTZ plans to recruit an additional 870 specialists for the operation and maintenance of the new line, while the project is expected to create approximately 1,300 jobs in total. Construction of the Kazakh section is scheduled for completion by the end of 2027.
Source: https://rail-news.kz/ru
The post KTZ completes 93% of earthworks on the 303 km Bakhty–Ayagoz railway line. appeared first on Transport Corridors.
This story was originally published by TransportCorridors. Read the full story at TransportCorridors →




Conversation