Seaway7 completes inter-array cable installation at East Anglia Three offshore wind farm
Seaway7 has completed the final inter-array cable lay at the 1.4 GW East Anglia Three offshore wind farm in the UK. Seaway7's teams installed 95...
Seaway7 has completed the final inter-array cable lay at the 1.4 GW East Anglia Three offshore wind farm in the UK.
Seaway7's teams installed 95 inter-array cables, totalling more than 240 kilometers of cable loaded, laid and pulled into the foundations at the site.
The achievement forms part of Seaway7’s wider scope on East Anglia Three, encompassing the foundations and inter-array cables for the project, and follows the completion of installation of all 95 monopile foundations and transition pieces earlier this year.
With cable lay now complete, testing, termination and trenching activities continue as we progress the remaining work towards completion of Seaway7’s full project scope.