EDECS Group Awarded DP World Contract to Upgrade Angola Port Infrastructure
EDECS Group, a MEA-region EPC contractor, has been awarded the Design & Build contract by DP World for the structural strengthening and upgrade of the quay wall…
EDECS Group, a MEA-region EPC contractor, has been awarded the Design & Build contract by DP World for the structural strengthening and upgrade of the quay wall at DP World’s container terminal at the Port of Luanda, Angola’s largest port. Covering the full 610-meter length of the existing quay wall, the project will enable the terminal to introduce rail-mounted Ship-to-Shore (STS) gantry cranes, marking a step in the modernization of its cargo-handling infrastructure.
Under the project scope, EDECS is delivering a package of structural, piling, crane infrastructure, and utility works required to transform the existing quay into a modern facility capable of supporting advanced STS crane operations.
The works include the installation of 120 piles, each measuring 1.0 meter in diameter and extending up to 45 meters in length. The piling works will be supported by a testing program, including ultrasonic cross-hole testing, high-strain dynamic testing, pile integrity testing, as well as working and non-working load tests to verify structural performance and long-term reliability.
EDECS will also construct a new reinforced concrete back beam on the landside and extend the existing capping beam. The company will also supply and install the complete crane rail system and associated quay furniture, including A150 crane rails, buffer stops, stow pins, tie-downs, cable drums, and panzer belt systems.
This story was originally published by Maritime Professional. Read the full story at Maritime Professional →